Maternity Hospital in Mykolaiv region

08.11.2024 SPP capacity: 85.8 kW Battery сapacity: 184.4 kWh Source of funding: Yellow-Blue Force Foundation Cost: 70 840 USD Expected electricity savings: 102 056 kWh

Nizhyn City Maternity Hospital, Nizhyn

20.03.2024 80 kW SPP capacity 65 kWh batteries 223 000 people can be treated if necessary Result In the first two months of operation, the plant generated 11.41 MW and […]

Myrhorod Intensive Care Hospital, Myrhorod

21.03.2024 32,5 kW Capacity of the solar power plant 38 447 people can be treated if necessary Result In the first two months of operation, the station generated 5.22 MW […]

Kremenchuk City Hospital “Pravoberezhna”

08.09.2023 60 kWt SPP capacity 50 000 patients per year capacity Result During the first month of operation (September 2023), the SPP generated 5,000 kWh. This amount of electricity covers […]