test – Ecoclub Rivne is an environmental NGO

test

loader-icon
loader-icon

07.06.2024


50 kWt

SPP capacity

40 kWh batteries

78 000 patients

can be treated annually at the medical facility


Expected result

Planned savings on utility bills: 17 155 per year

Source of funding

funds were provided by the Yellowblue Force Foundation.

Cost: 76 262 USD of which 7 626 USD is a community contribution


20.03.2024


80 kW

SPP capacity

65 kWh batteries

223 000 people

can be treated if necessary


Result

In the first two months of operation, the plant generated 11.41 MW and saved about 71 thousand hryvnias

Source of funding

Yellowblue Force Foundation


21.03.2024


32,5 kW

Capacity of the solar power plant

38 447 people

can be treated if necessary


Result

In the first two months of operation, the station generated 5.22 MW and saved about 30 thousand hryvnias

Source of funding

The equipment was provided with the support of Astrid Schneider, while the development of project documentation and the construction of the solar power plant were funded by the community


29.12.2022


32,4 кВт

SPP capacity

170 000

patients per year capacity


Result

During the first month of operation (January 2023), the station generated 800 kW. This energy is enough for a month’s constant work of one medical ventilator.

Source of funding

 Funds raised via webathon “Sustainability4Ukraine” from CSR.Europe, CSR.Ukraine and Dobro.UA


26.06.2023


43,6 kWt

of SPP capacity

170 000

people can be treated in the medical facility if needed


Expected result

Planned electricity savings – 154 700 UAH per year ( according to the 2022 tariff).

Source of funding

Total cost: 40 222 USD. 26 870 USD – funds from the Embassy of Germany in Ukraine. 11 720 USD – municipality budget. 1 632 USD – NGO Ecoclub.


05.07.2023


60 kWt

of SPP capacity

277 500

people can be treated in the medical facility if necessary


Expected result

The planned electricity savings – 457 500 UAH per year (at the 2022 tariff).

Source of funding

Total cost: 46 809 USD. 29 936 USD – raised by the NGO Ecoclub together with donors from Poland, the Czech Republic and Germany. 16 873 USD – municipality budget.


04.07.2023


48 kWt

of SPP capacity

118 000

people can be treated in the medical facility if necessary


Expected result

Planned electricity savings – 307 000 UAH (at the 2022 tariff).

Source of funding

Total cost: 36 129 USD. The equipment for the solar power plant was provided by the Czech company SOLSOL with the support of the NGO NESEHNUTI.


08.09.2023


60 kWt

SPP capacity

50 000

patients per year capacity


Result

During the first month of operation (September 2023), the SPP generated 5,000 kWh. This amount of electricity covers the weekly operation of the hospital’s therapeutic department.

Source of funding

Total cost: 45 598 USD. The equipment for the solar power plant was provided by Elektrizitätswerke Schönau with the support of the WECF (Women Engage for a Common Future).


21.12.2023


71 kWt

SPP capacity

104 157

patients can be treated annually at the medical facility


Expected result

Planned savings on electricity bills – 1 383 USD per year (at the 2023 tariff)

Source of funding

SPP provided by PV Exchange with the support of Ideen hoch drei e.V. and Astrid Schneider


04.10.2023


33,5 kWt

SPP capacity

About 170 000 patients

visit the facility annually


Expected result

The SPP will cover about 30% of the dentistry’s electricity needs. The planned savings will be about 3 846 USD per year (at the 2023 tariff)

Source of funding

25 320 USD was provided by the Embassy of Germany in Kyiv. 50 374 USD – community budget.


04.01.2024


66,4 kWt

SPP capacity

7 550 patients

can be treated annually at the medical facility


Expected result

The planned savings will amount to about 13 175 USD per year (at the 2024 tariff)

Source of funding

Equipment worth 28 318 USD was provided by PV Exchange with the support of Ideen hoch drei e.V. and Astrid Schneider. 21 246 USD is a contribution from the community.


loader-icon

21.05.2024


Power of the SPP

50 kW

The water utility provides water

16 190 population


Expected results: planned generation during the year: 84,358 kW

Source of funding: The total cost of the SPP is 54 270 USD. Of this amount, LLC BOHUSLAVENERGY provided 49 330 USD, and the community contributed 4 940 USD

00.00.0000


Power of the SPP

100 kW

The water utility provides water

8 254 population


Expected result: The SPP will produce 106,634 kWh per year. This will cover 13.5% of the company’s annual electricity demand.

Source of funding: 86 779,91 USD was allocated from the community budget.

03.05.2024


Power of the solar power plant:

67.8 kW,

batteries: 56.32 kWh

The water utility provides water to

48 670 people


The system can operate autonomously for about 1.5 hours.

Projected annual generation – 87553.33 kWh/year 

Cost: 84100 euros. Of this amount, 70,000 euros were allocated under the Oxfam project, and 14,100 euros were contributed by the community

02.05.2024


Power of the SPP

72.45 kW,

batteries: 61.44 kWh.

The water utility provides water to

32 000 people


Projected annual generation: 75800 kWh/year

Cost: 77059 euros. Of this amount, 70,000 euros were allocated by the Oxfam project, and 7050 euros were contributed by the community.

01.05.2024


Power of the SPP

100.57 kW,

batteries: 81.6 kWh

The water utility provides water

256 000 population


Projected annual generation: about 115,000 kWh/year

Cost: 135500 euros. Of this amount, €120,000 was allocated as part of the Oxfam project, €15,500 was the community’s contribution